Department Update

Calendar week 42 and 43 conclude the efforts of a combined CMI US and China team in auditing our HSM assembly line, and key HSM component sub-suppliers.
In CW42, John L., Mike H., Alex H. and Chun Y. visited Younghshin's assembly line supplier Shin Yang in Daegu Korea. The visit showed the impressive capability of Youngshin's automated assembly supply base. The assembly line includes critical machines like the Tip-Clearance and bearing-to-bearing alignment machine that performed above expectation and met CMI's high-bar for error proofing in this critical step.
The first HSM from the line was produced with all 9 stations outputting OK status to the SPC quality system. The combined CMI/Youngshin/Shin Yang team signed this unit to be displayed in CMI to remember this milestone.

Over to you, CMers
What Car is this?

One new car for you to guess....
What is this?

Get your heads around this...
Or submit your answer(s) on Teams channel #general

We're really pleased you are enjoying Bob as much as we are. Thank you to those who have completed their Onboarding, if you have yet to complete the HiBob onboarding, please complete it as soon as possible.
Our October Values Nominees
Abell Veguilla
I would like to nominate Abell Veguilla for #Pioneering, as a new employee he did not hesitate to jump in and work to get 36 FAA's wrapped packaged and sent to Baolong.
Lorna Mayer & the HR team
I nominate Lorna Mayer for her #extraordinary effort with the whole HR team (Grace, Grace, Lucas, Jerry, Elli) to introduce an extremely friendly system "Bob" to our organization. I LOVE being able to see a complete organization chart. Thanks for your hard work team!
(Lorna will not receive a gift card if won)
Alexander Hale, Michael Hogg, John Lowry & Chun Yan
I would like to nominate Alexander Hale & Michael Hogg & John Lowry & Chun Yan for #Collaborative as they did the excellent cross function audit to our core supplier------Yongshin in Korea last week. This audit provides assurance for future supplier quality management.
Rajinder Singh & Matthew Pate
I would like to announce that V10 EMM TT PCBA design has been successfully signed off by our #collaborative and #extraordinary electronics team, Rajinder Singh and Matthew Pate. This is a significant first milestone in our journey (towards V11 E/E EMM design) where the team went above and beyond what is expected from a typical customer/supplier relationship by taking the lead and guiding Sona into more robust and cost effective V10 EMM.
Dinakar Gudladona
Big thankyou to Dinakar Gudladona for being #collaborative and #extraordinary for agreeing to travel to Sona last week at the last minute to push and hold Sona accountable for a topic outside of his responsibilities! The bonus being that he helped to resolve the issue and ensure delivery of future DV EMMs! (just the pesky heli-coils rearing the head now!)
Antonio Saorin, Graham Dowie & Timothy Light
I'd like to nominate Antonio Saorin, Graham Dowie and Timothy Light for their #Collaborative and #Extraordinary effort in regards to the above and beyond support they gave myself and Harry Schneider in China, often speaking to with the guys well into the night US time and very early mornings UK time so that we had practically 24 hour support for tuning and data analysis.
Marian Ionicoiu & Knight Li
Marian Ionicoiu & Knight Li, having recently joined the IT team, they’ve hit the ground running as new employees. Marian has taken great initiatives to help support me & identify areas for improvement to our IT systems and processes. Secondly Knight for jumping in at the deep end from the get-go, setting up our new IT systems in China. #resilient efforts between time zones! #extraordinary & #collaborative with a global mindset.
Lu Fang, Yongjie Shi & Chun Yan
I'd like to nominate Lu Fang & Yongjie Shi & Chun Yan for their #Collaborative and #Extraordinary effort in regards to solve the cost of brackets and gaskets, potential sourcing resource of manifold and pigtail. They did great effort by day and night in past month to get significant achievements in sourcing. As supplier quality, I appreciate their hard work for this,
Neil Gudgeon, Alexander Danglidis & Harry Schneider
The #extraordinary, #resilient and #collaborative Neil Gudgeon, Alexander Danglidis and Harry Schneider. Over the past 21 days, Neil, Alex and Harry have been working tirelessly on Mule tune loop 2 with Hailin, going above and beyond to ensure its success. Even during the busy Golden Week in China, they chose to put the project's needs first and took only 1.5 days off!